INSPECTION SCHEDULE

ADDITIONS/NEW DWELLING (5 INSPECTIONS) – NEW DWELLING HOUSE NUMBER MUST BE POSTED AT THE STREET LINE BEFORE INSPECTIONS ARE DONE

1. FOOTING

       KEYWAYS OR RODS

2. FOUNDATION

COAT WALL

FOUNDATION AS BUILT MUST BE SUBMITTED BEFORE THIS INSPECTION IS DONE FOR A NEW DWELLING

3. ROUGH FRAME

ROUGH ELECTRICAL AND PLUMBING INSPECTIONS MUST BE COMPLETED.

PRE INSULATION DONE
INSULATION BEHIND ELECTRICAL OUTLETS ON OUTSIDE WALL.
BAFFLES WHERE REQUIRED
HOLES PLUGGED BETWEEN FLOORS

4.   INSULATION

COPY OF MASCHECK COMPLIANCE REPORT MUST BE AT JOB SITE.

WALLS, CEILINGS BOTTOM OF 1st FLOOR, PLUG WINDOWS AND DOORS AND ANY OTHER OPENINGS.
        
PAGE 1 of 2

INSPECTION SCHEDULE

5. FINAL

ALL SAFETY ISSUES COMPLETED.

NEW DWELLING – BEFORE INSPECTION IS DONE, HOUSE NUMBER MUST BE POSTED, THREE-INCH SIZE, ON THE HOUSE IN CONTRASTING COLOR FROM THE HOUSE.  IF HOUSE IS TOO FAR FROM THE STREET, AN ADDITIONAL NUMBER WILL BE REQUIRED AT THE STREET LINE AND SHOULD BE VISIBLE FROM BOTH DIRECTIONS OF THE STREET.

FINAL ELECTRICAL, PLUMBING AND FIRE INSPECTIONS MUST BE COMPLETED BEFORE FINAL INSPECTION IS DONE BY THE BUILDING INSPECTOR.