The permit fee covers the number of inspections indicated for the type of construction. There is a $25 fee for any additional inspections over the amount indicated.
- Decks (2 inspections)
- Excavating inspection
- Sona tube hole inspection - before concrete is poured.
- Final
- Above-ground pool (1 inspection)
- Final
- Fencing, self-closing gate, and alarms should be completed before this inspection is done
- Inground pool (2 inspections)
- Formed with rebar in place
- Fencing, self-closing gate, and alarms should be completed before this inspection is done
- Garage (3 inspections)
- Footing
- Foundation
- 3) Final
- Safety cable to spring
- Page 1 of 2
- Miscellaneous Inspections
- Garage - Attached To House (4 Inspections)
- Footing
- Rough Frame
- 4. Final
- Fire Door
- Firewall
- Safety Cable to Spring
- Shed (1 Inspection)
- Wood Stove (1 Inspection)
- Chimney (1 Inspection)
- Fireplaces (2 Inspections)